Interconnection Guidelines
- Click on this outline of the entire process to access information needed to successfully install solar equipment at home and connect a distributed generation system.
All interconnection applications must be submitted online through PowerClerk.
Before you start, please have:
- A system diagram (showing your equipment, meters, and disconnect switch if required)
- A site plan (showing equipment locations and your system’s address)
- Proof of insurance
- Equipment certification or compliance documents
- Manufacturer specification sheets
Required Forms (completed in PowerClerk)
- Wisconsin Standard Distributed Generation Application
- Supplement for Solar, Energy Storage, Wind, or Generator (as needed)
- Interconnection Agreement
Visit PowerClerk today to begin your application.